Monday 23 March 2015

Update

Has been a very busy week. Electricians removed sub board and ran all circuits to MSB as promised. They also re ran shed feed and left remaining length coiled up awaiting trench. General electrical work I still find does not meet standards but have decided to not pursue the issues any further.
Air con was installed but did not fit between joists. 2 were removed to accommodate the unit. JG Kings framers came to site and rectified the issue within a day. Was very happy with the result and how the situation was handled; Kings could have blown the issue out of hand if they wanted to.

Insulation has now been 50% installed but bricks are yet to start.