Electrcians are revisiting site today.  SS has been good with the issues and Switchboard in halllway is being deleted (all circuits will go to meter box as per drawings). A new cable will be run to future shed location and not cut. I have also left a list of other issues,  mainly about cable installation,  support and damage that could arise when ceiling is accessed after handover. I have contacted Energy Safe Victoria and they have confirmed the electrical works are well below standards. 
Scaffolding has been removed as all roof works are now complete.

Aircon is also being installed today. Looking forward to results tonight.