Insufficient clearance betweem LPG bottles and HWS (800mm, 1500mm required)
Large hume entry door is heavily water stained.
Ceserstone bech top has been scratched.
Window seals warped and coming away from windows.
New plasters started Monday, electricians cut out Tuesday and painting began Wednesday. I was unable to access the house during the week, but managed to get in yesturday. Plastering is still very far from the quailty that's expected and if anything, the paint has made the workmanship more visible. Have meeting with SS on site tomorrow. See attached picture of cornice join.
Been an interesting week. Got a call from Kings saying our Site Supervisor is no longer managing our build and put me onto our new one. Did not get a great feel with this supervisor which means I will need to start keeping a very close eye on things again.
Plastering is STILL not completed and still full of defects.
Eves were finished this week. Very slow going.
Kitchen and cabinetry in the bathrooms has now been installed. Happy with the quality. Plastering has been imporved, but still needs some work to be up to scratch. Eves have been delivered to site.
Brickwork now looks to be complete (apart from acid wash).
Plastering is still not completed and still requires sanding. As mentioned in previous posts I have quite a few issues with the quailty of plastering, but SS has insisted it be complete before they are looked at. Plastering process in nearing a month now, which is a bit disserpointing.
I have made a list of windows that are bowed and will pass this onto SS. Some are to the extent that they do not seal and allow air to pass freely.
We are also trying to change the color of our roller door and water tank (Ironstone color we chose is alot more blue than expected); Kings are not being very helpful with this. They initally said no as it was "already in the system". We have requested they try a little harder and told them we are prepared to pay a variation fee if required.
Finally we received a letter from Kings on Friday stating that the company they engaged to do our cabinetry/kitchen is now "unable to do so". I suspect this means they have gone broke. The letter told us to expect delays due to this. I would not be suprised if the delay is a month or two. With this said we are glad our kitchen was not installed by the company before they went broke and are prepared to wait as long as we recieve a quailty job.
It occurred to me today that it has been some time since I have made an update to the Blog. This is basically because there has not been much to blog about!
Brick layers are still chipping away and quality of their work seems good. They expect to be finished by mid next week.
Plastering is still not complete but does seem very rough. I highly doubt the finish will be what I expect. They have also hung cornice in two rooms that are on the plans as square set. SS recommends we wait until the plasters are completely finished before defecting the work.
With the installation of the plaster it has also come to light that some windows are not sitting correctly and need to be adjusted.
We have sacked out independent inspector as I have found he has missed far to much for me to be confident in him. We will not be replacing him at this stage as I feel I am on top of things myself.
More plaster hung today, but still some to go. Plaster has been sheeted on the unbricked garage wall (and also unwrapped/uninsulated) which is concerning as it will get wet if it rains or could take on moisture on a cold night. Will be watching this closley.
I estimate 70% of the house has now been sheeted. Gives us a good feel for the room sizes.
About 30% of bricks have been laid. As said before they are very dark when first laid, but show their real appearance about 48 hours later.
Plasterers sheeted the ceiling today and made a start on the walls. Bricklayers are going at a steady pace and quality looks great. Bricks have now became lighter as they have dried and we are much happier with the chosen colour.
Insulation has now been completed. Quality seems ok, I filled in any gaps myself (apart from where downlights are to go) this afternoon.
Brick work is coming along, looks to be only two men bricking, so hopefully it will be a well done job, even if that means it does take a bit longer. Myself and my wife are both a bit suprised at how dark the bricks look from a distance, it could also be to do with the mortar we chose.
Plaster is 10mm thick and Knauf brand, along with top coat etc. Plastering yet to begin.
Brickwork began yesturday. Bricks are looking darker than what we had expected, but I did visit site just on dusk. Plaster has been delivered. Insulators were still at site (all 5 of them traveling in the same van) at 8pm and said they would be finished that night. They had a heap of work ahead of them, and I suspect they would not be completed until midnight or after.
On a different note, I had my wife record a 30 minute video of me measuring stud distances and where water and gas piping is located in the house for future reference.
Suspecting plaster will be sheeted today.
Electrcians are revisiting site today. SS has been good with the issues and Switchboard in halllway is being deleted (all circuits will go to meter box as per drawings). A new cable will be run to future shed location and not cut. I have also left a list of other issues, mainly about cable installation, support and damage that could arise when ceiling is accessed after handover. I have contacted Energy Safe Victoria and they have confirmed the electrical works are well below standards.
Scaffolding has been removed as all roof works are now complete.
Aircon is also being installed today. Looking forward to results tonight.
Solar hot water panel has now been installed.
Being steel frame, it is required to install timber noggins wherever anything heavy will be hung from a wall (such as a TV). I have started installing where needed.
Aircon rep showed up yesturday, and did not fill me with much confidence. Earliest they can rough in is 23rd of March, a date I feel is too late (plaster may be on by then). Could not contaact SS to get a plaster hang date, will try again today.
Roofing was competed on Tuesday. No works on Wednesday or Thursday but on friday the following was achived :
Bricks delivered to site
Plumbing Roughed in (both water and gas)
House wrapped ready for brickwork.
External doors installed (including our large hume front door)
So from what I can see, once brickwork is complete the house will be at lockup. Two issues have arisen this week; both issues with my own contractors not the builder
1. My independent inspector carried out the frame inspection and reported an overall high quality job. What he did not pick up though is the incorrect location of the WIL door that Kings have yet to correct. (SS is aware and guarantees me it will be relocated). Because of this im feeling he is not as thorough as I expect and may need to arrange a different inspector for future inspections.
2. Air con contractor cancelled appointment on Wednesday to meet at site to discuss location of indoor and outdoor units, along with ductwork. He has not contacted me since and I have lost alot of faith in the company. I emailed the contractor today stating that the house was nearing lockup. Waiting for response.
Colourbond roof 80% installed today. Ironstone colour, same as gutters but looks very different depending on the angle.
Progressing very quick
Driving to work this morning I realised that the access door position to the WIL is in the incorrect position. The doorway needs to be on the far left as per plans (currently on far right) or access will be hindered due to washing machine space. I have emailed SS with photo this afternoon but am yet to hear back. Looks like a relatively simple fix but I am glad I picked it up early.
Site looks like it was cleaned up with a bobcat today, exervated rock was moved to outside of site area and crushed rock has been spread at base of house to assist bricklayers.
Guttering has now been installed. All frame looks to be competed apart from front and rear garage wall.
No other materials are on site so I am excecting a lull for a few days.
Frame now looks mostly complete apart from some bracing. Aircon contractor meeting with me at site later this week to discuss internal ceiling mounted unit location.
Happy with progress.
Frame erection begun today, 19 days after slab pour. I was suprised as we had some very heavy rain and thunderstorms , but at least 70% of the frame has been stood up. Garage is still on ground.
Rooms feel very spacious and no surprises as far as layout. Hallway as pictured gives a good indication of the length of the house design.
My only concern is the amount of steel in the roof. We have engaged an external contractor to install a Ducted RC aircon which requires a large unit in the ceiling. It will be challenging for the unit to be installed without effecting the structural integrity.
I wouldn't be surprised if frame is completed tomorrow.
Frame delivered today. JG King uses a steel frame design as oppose to timber. Although it wasn't a deal breaker when selecting a builder, I personally prefur the steel frame as I have good experence working with it in a commercial environment.
Bluescope steel branded, frame seems good quality. Walls are assembled and ready to stand as along with the roof. Sharp edges all around, gloves would have to be used when erecting.
SS expects frame to begin erection this week.
Met a local Bobcat operator at site this morning who I required to spread/level the crushed rock driveway more evenly. Great result.
Charge was $80ph with a minimum of 4 hours, costing $320.
This brings the total cost for the access driveway to $1620
I calculated we required about 40sqm of cubic crushed rock to make an access track to the house location as requested by the builder. Frame is arriving monday so only had 5 days to get it done.
The track will eventually be the base for a permanent driveway after the house is built. I decided on 40mm crushed rock (over the standard 20mm) as it is better suited to heavy vehicles.
I suggest anyone purchasing rock or soil in this quantity try organise a truck owner/driver to source directly from a quarry, it halved our cost compared to a local sand and soil buisness.
An old friend owns a Truck and Trailer and I was able to track him down. Was a paid job, but I knew he was reliable and had an account at a few quarrys. He also was able to put chains on this truck and trailer to slowly spread the rock instead of just dropping it in a pile. This will help alot with spreading the rock evenly.
I have a bobcat and operator arriving Sunday morning to do this.
Total cost of the rock was $1000 (53 tones, approx 38m). This took up 2 full truck and trailer loads, delivered in 2 consecutive nights. $300 cash to my old friend for the delivery was money very well spent.
Slab poured on Wednesday as promised. Footings at alfresco and entry; I assume top of these areas will be done at later stage. House size now seems to look alot larger. SS has promised frame delivered Monday and erection started by end of next week. Things are moving very quickly.